KMS was awarded the project to construct the new CV025 Curved Conveyor under 2 phases as part of the Mine Expansion Project at CMOC Northparkes Mines. The first phase involved setting up of concrete footings, assembly and installation of conveyor steel modules, and post construction survey. In the second phase, KMS undertook the construction of CV025 head-end and tail-end infrastructure including modifications and tie-in to existing conveyor systems.

The project was completed successfully within schedule and budget without any safety incidents.

Timeline – Oct 2020 – Feb 2021
Man hours – 5300 hrs.
Project Value – $800,000

Conveyor plinths for the CV025 Project
Conveyor plinths for the CV025 Project
Conveyor plinths for the CV025 Project
Conveyor plinths for the CV025 Project