Skip to content
Truss

Projects

Welding. Metal Fitting. Engineering. Fabrication. Shutdown Labour. Civil Works. Pipework & Poly Welding.

T1 & T2 Tressel Infill SMP

T1 & T2 Tressel Infill SMP

Project scope was to set out foundation civils, install infill shells and fill trestles with concrete.

ML01 & ML02 Mill Replacement SMP

ML01 & ML02 Mill Replacement SMP

KMS were awarded the structural steel and mechanical package to replace all existing platforms, chutes, lube units and piping, steelwork, guarding, blast and paint and commissioning of mechanical items.

Mineral Hill Processing Plant Refurbishment

Mineral Hill Processing Plant Refurbishment

KMS fabricated and lined brand new chutes and screen, conveyor skirting, replaced all the structural steelwork through the plant, installed all the pumps and pipework, this project had a duration of 18months to complete.

GDT Recycling Plant Supply & Install

GDT Recycling Plant Supply & Install

KMS were awarded SMP package to fabricate all load tubes, infill frames, structural steelwork, mechanical items and piping. KMS were also awarded to install all the items for modules 5-4 and commissioning.

Shaft 1-2 Cooling Tower SMP

Shaft 1-2 Cooling Tower SMP

Scope of this project was to fabricate all structural steel for shed, fabricate and supply all stainless piping and construct all items and commission.

GDT Recycling Piping Package

GDT Recycling Piping Package

KMS supplied nitrogen and water piping for GDT, all piping was hydrostatic pressure tested and QA.

Apron Feeder Refurbishment

Apron Feeder Refurbishment

KMS removed all existing mechanical items on apron feeder and replaced all items as new and commissioned.

Design & Construct Screwpress

Design & Construct Screwpress

KMS was approached to design the screw press structure, fabricate all items and install.

CV25 Conveyor SMP

CV25 Conveyor SMP

KMS completed the install of 1.5km of conveyor steel stringers, part of this project we completed survey set out of the entire conveyor.

Vent Fan Refurbishment

Vent Fan Refurbishment

Replacement of all existing corroded fan ducted components, replaced propeller and shaft, laser aligned shaft and lobster back duct, all items grouted and commissioned to speck.

CR01 Chute Package

CR01 Chute Package

KMS were awarded the full package of the flow system for CR01 crusher circuit.

Process Water Line Replacement

Process Water Line Replacement

KMS were awarded as part of our poly contract at North Parkes Mines to replace the 630mm process water line, we replaced this line in under 3x shafts as the entire processing plant needed to be shutdown to complete these works.

Fourth Tails

Fourth Tails

As part of Ore Processing Department upgrade to accommodate higher production rates, a fourth tails line was required to compensate greater flow rates and to allow for maintenance works to be carried out without impacting production.

Shaft 1 & 2 SMP Cooling Upgrade

Shaft 1 & 2 SMP Cooling Upgrade

KMS was contracted to provide comprehensive fabrication and installation services for the construction of a permanent bulk air cooling (BAC) facility for Shaft 1 & Shaft 2.

Grizzly H-Frame Install

Grizzly H-Frame Install

KMS were awarded to install the grizzly H-frame for CR01 crusher, this steelwork needed to be installed in situ and welded out in place due to the size of the components.

Flask Tipping Cradle Fabrication

Flask Tipping Cradle Fabrication

KMS were awarded to fabricated 2x tipping cradles for the underground loading station, we were also awarded the install of both these items.

CY02 Re-Assignment

CY02 Re-Assignment

Due to the ongoing operational and maintenance challenges with the existing ML002 feed configuration, and CY002 structure being at the end of its operational life, a new cyclone design and location was recommended.

Secondary Crusher Upgrade

Secondary Crusher Upgrade

KMS were engaged by local client to complete civil & earthworks, fabrication, paint, and installation of a new Belt Magnet structure.

Scoop Rebuild

Scoop Rebuild

KMS re-engineered the existing scoop and replaced all worn components and certified this unit to current standards for compliance. This unit was preload test for operation before delivery as part of the certification.

Slurry Pipe inspections (MOD1)

Slurry Pipe inspections (MOD1)

Slurry Pipe inspections (MOD1)

Steel sets

Steel sets

Steel sets for North Parkes Mines. Custom fabrication.

Reclaimed tunnel

Reclaimed tunnel

The KMS team been busy installing the reclaimed tunnel for North Parkes Mines.

Conveyor plinths for the CV025 Project

Conveyor plinths for the CV025 Project

KMS was awarded the project to construct the new CV025 Curved Conveyor under 2 phases as part of the Mine Expansion Project at CMOC Northparkes Mines.

KMS was assigned the task of repairing a 250mm crack on one of the mod2 mills.

Crack repair Mod2 Mills

KMS were assigned the task of repairing a 250mm crack on one of the mod2 mills.

Rosedale Surface Infrastructure Flood Line

Rosedale Surface Infrastructure Flood Line

The KMS team have been welding poly with the T900 Tracstar for the flood line at the Rosedale Surface Infrastructure Project at Northparkes Mines.

Sag Mill Discharge Chute

Sag Mill Discharge Chute

Our KMS team have been working around the clock to hit the delivery date to fabricate this 6t discharge chute for a sag mill @ Northparkes Mines, we still have rubber lining and a three coat painting system to go before completion.

CV002 Conveyor Gearbox

CV002 Conveyor Gearbox

The KMS team have completed the CV002 Conveyor Gearbox and structural steel upgrade at Northparkes Mines which will increase the speed and tonnage on the conveyor, this project is in line with the expansion project.

Surface Feeder

Surface Feeder

Surface Feeder had metal fatigue and was days away from a failure, KMS replaced the feeder floor along with the removal and re-in-stall of the subframe.

Open Cut Pit at North Parkes Mines

Open Cut Pit

The view from the bottom! This week the team were approx 150 meters down in the Open Cut Pit onsite at Northparkes Mines replacing the wet end on the pump.

Man Cage

Man Cage at Northpark Mines

The man cage that connects to our L60E Loader which will be heading underground at Northparkes Mines.

Installation of a Mill Deck Slew Crane

Installation of a Mill Deck Slew Crane

Installation of a Mill Deck Slew Crane

Rebuild FT50 Float Tank

Rebuild FT50 Float Tank

Rebuild of the FT50 Float Tank at North Parkes Mines

Northparkes Mine - E26 Crusher

Northparkes Mine - E26 Crusher

Northparkes Mine - Rebuilding the E26 Crusher

Tailings Poly Line installation

Tailings Poly Line installation

Tailings Poly Line installation project at Northparkes Mines

TIG Welding

Stainless Steel TIG Welding

KMS completed stainless steel pressure tig welding on a boiler room in a shutdown, build duration 5 days.

Northparkes Mine - Valve and spool change out

Valve & Spool Change Out

KMS replaced 2x 600lb crane valve and fabricated and installed 2x 6” spools on the North Parkes Mines underground dewatering line.

6inch Stainless Blower Lines

6inch Stainless Blower Lines

Upgrade works to the stainless blower lines

Cleaners Project

Cleaners Project

Flotation upgrade to increase input of cons through the OPD circuit. Works included installtionof new pumps, fabricated and installed new dart valve tanks, installed new 280 poly pipe work throughout the circuit.

Hanson Concrete

Decommission Batching Plant

Decommission of Batching Plant at Hanson Concrete NSW.

Oliver

Door Oliver Refurbishment

Reburish 8 x float tanks to be in line with the expansion project, work incuded was cut out coordied floor panels, welding in new sections, blast and paint entire cells for protection. Design, fabricate and install new stainless steal blower lines for rotors.

2019 Machine Guarding Compliance

Machine Guarding Compliance

Fabricated and installed conveyor guarding through out the OPD area at Northparkes Mines.

ML03 Discharge Chute

ML03 Discharge Chute

Fabrication and Upgrade of the ML03 Discharge Chute at NPM

Reagent Yard Upgrade

Reagent Yard Upgrade

Replacing the reagent t pump manifolds

Secondary Magnet SMP

Secondary Magnet SMP

Secondary Magnet SMP

Special Piping Project

Special Piping Project

Fabrication of various slurry pipes from DN150 - DN550, pipes where cermanic and rubber lined at clients request.

KMS - Kitson Manufacturing Solutions 47
Fan hangers
Welding workshop
KMS - Kitson Manufacturing Solutions 30
KMS - Kitson Manufacturing Solutions 36
Back To Top